A switchgear lineup can only be designed around the information that defines its electrical duty, connected loads, physical setting, and project interfaces. A design-input register brings utility data, one-line diagrams, load schedules, and site constraints into one reviewable record. It also separates confirmed facts from assumptions and unresolved decisions, so a quotation and preliminary design do not quietly depend on missing or conflicting information.
Establish the electrical source and duty
Start with the serving utility’s available fault-current information at the proposed service point, including the basis and date of the data, and identify the source configuration expected during normal and alternate operation. Record system nominal voltage, frequency, grounding method, transformer details when known, and any planned generation or parallel sources. A voltage label by itself is not enough to define equipment duty: nominal system voltage and the equipment’s maximum rating are related but distinct values that must be coordinated for the specific application.
The one-line should show the intended service arrangement, main and tie devices, transformers, feeders, metering, protective devices, and points of connection. Flag differences between the drawing and utility documents rather than choosing one silently. Available fault current, protective-device characteristics, and the required short-circuit rating affect selection and coordination; if these inputs are pending, state what must be confirmed and who is responsible. Do not treat an assumed fault-current value as a verified design condition.
Make load schedules traceable to the one-line
For each feeder, provide a consistent identifier, destination, load description, voltage, phase, estimated or calculated demand, and any known motor or other starting characteristics. Include the load schedule’s revision and design basis, such as whether values represent connected load, demand load, or a preliminary estimate. Identify spare devices separately from future loads: a spare position reserves physical or electrical provision, while a future load may require a defined rating, control interface, or protection approach.
Reconcile feeder names and quantities across the schedule and one-line before design review. Note loads that are intermittent, nonlinear, sensitive, or expected to expand, since these details may affect metering, component selection, heat, and future space. Where the load information is incomplete, record the decision needed rather than inserting an unmarked assumption. A buyer seeking a quote should supply the latest one-line and load schedule, explain known discrepancies, and identify the person authorized to resolve them.

Capture operating intent and protection interfaces
Document how the lineup is expected to operate, not just how it is drawn. Clarify whether a tie is normally open or normally closed, whether transfer is manual or automatic, and what interlocks or operating restrictions are required. Identify the intended protective-device functions and available coordination or arc-energy study inputs, while distinguishing required functions from preferences. These decisions can change device types, control wiring, compartment arrangements, and the information needed from the project’s protection engineer.
List interfaces with upstream and downstream equipment, including cable or bus connections, control power, external trip or close signals, communications, metering, and remote status points when applicable. Define who supplies each interface and who provides associated cables, settings, programming, and testing. If a study or control narrative is not yet available, mark it as pending and describe the design hold point. Final protection settings and system coordination depend on project-specific studies and must not be inferred from a preliminary lineup schedule.
Measure the site envelope and installation constraints
Provide the available room dimensions, lineup location, access route, door and corridor clearances, floor or housekeeping-pad information, and the intended cable-entry direction. Identify adjacent walls, columns, overhead obstructions, existing equipment, and any restriction on assembly length or shipping sections. These inputs can determine whether a proposed arrangement is physically workable and whether cable bending space, maintenance access, and equipment removal paths can be preserved.
Describe environmental and site conditions that affect the design basis, such as indoor or outdoor placement, ambient temperature range, altitude, moisture, dust, corrosion exposure, and seismic or other applicable project criteria. For a Dallas–Fort Worth project, provide the actual site and room conditions rather than relying on regional assumptions; the same principle applies to shipments elsewhere. Confirm receiving access, unloading responsibility, and any packaging or delivery constraints. Site suitability and installation provisions require review against the project specification and equipment details.
Keep assumptions, revisions, and decisions visible
A useful register gives every input a source, revision or date, status, owner, and disposition. Mark information as confirmed, preliminary, assumed, or unresolved, and connect open items to the drawing or specification affected. Record the consequence of a missing answer, such as a rating still to be selected, a footprint not yet validated, or a control interface awaiting confirmation. This makes the review actionable and prevents an assumption from becoming a requirement merely because it appeared on an early drawing.
Use a revision-controlled package to compare the one-line, load schedule, equipment specification, site plan, and interface documents. The resulting review record can include a design-input register, an assumption and open-decision log, a marked-up one-line, a preliminary lineup arrangement, and a list of required customer approvals. These are planning outputs, not a substitute for final engineering documents or approved-for-construction drawings. Resolve conflicts through the designated project authority and retain the decision with its source and date.
Define quote scope and confirm order-specific requirements
For a useful quotation, provide the electrical and physical inputs above together with the project specification, required drawing submittals, delivery destination, requested schedule, and any applicable domestic-content or U.S.-origin requirements. Identify whether the request is for a new custom-built assembly and clearly state included and excluded scope, such as protective relays, metering, controls, studies, field services, or installation. Equipment configuration, component availability, ratings, standards, and origin requirements must be checked for the particular order; none should be assumed from a generic checklist.
A manufacturer can use the package to review design choices, identify missing inputs, and develop a proposed new-equipment configuration. UL 891 may apply to low-voltage switchboards when appropriate to the specified assembly, but it is not a general designation for medium-voltage equipment. Shorter lead time may be a goal, not a guarantee, and depends on confirmed design, components, and order conditions. Before release, the purchaser and manufacturer should agree on the governing documents, unresolved decisions, responsibility boundaries, and the basis for all ratings and compliance statements.
Specifications & planning
Review the details that matter for your application. Final specifications and availability should be confirmed for your project.
| Evaluation factor | Input to review |
|---|---|
| Electrical duty | Utility fault-current data, source arrangement, grounding, and rating basis |
| Load definition | Feeder-level demand, load characteristics, spares, and future provisions |
| Physical fit | Room envelope, access route, cable entry, clearances, and site conditions |
| Interface clarity | Operating sequence, protection inputs, control signals, and scope ownership |