Power distribution, with purpose.
Custom switchgear starts with the conditions the equipment must meet, not with a cabinet sketch or a preferred product name. For a new build, document how the assembly will connect to the system, fit the available space, operate with adjacent equipment, and support the facility’s control strategy. The manufacturer builds new equipment and can evaluate project-specific requirements; final capability, components, ratings, standards, and U.S.-origin requirements must be confirmed for the particular order.
Define the electrical duty before choosing an assembly
Provide the one-line diagram and identify the system’s nominal voltage, phase, frequency, grounding method, and expected operating arrangement. State whether the project calls for a low-voltage switchboard, medium-voltage switchgear, or another assembly type. Voltage terminology matters: a system’s nominal voltage is not the same as an equipment maximum rating, and the required rating must be established for the application rather than inferred from a nominal value.
Include available fault-current information, required short-circuit ratings, protective-device details, and any source or tie configurations that affect duty. If the study is pending, say so and identify who will provide the final data. The manufacturer and project engineer should review these inputs together before the design is finalized. A low-voltage switchboard built to UL 891 is a distinct equipment category; UL 891 should not be applied as a blanket claim to medium-voltage equipment. Applicable standards and any required listing or labeling must be confirmed for the specific assembly.
Translate the room and installation into mechanical requirements
A custom design must fit its actual route and operating environment, not just the room plan. Supply available width, depth, and height; access and service clearances; floor and support details; conduit or bus entry zones; and restrictions at doors, corridors, elevators, or loading points. Identify whether sections must be moved separately and reassembled, and note any seismic, environmental, or enclosure requirements established by the project documents.
Explain where the equipment will operate and what may affect its construction, including indoor or outdoor exposure, ambient conditions, dust, moisture, corrosion concerns, and nearby heat sources. Describe how incoming and outgoing conductors will approach the assembly and where field connections must land. These details can create tradeoffs between footprint, maintainability, cable bending space, and future expansion. A dimensioned room plan and installation constraints are more useful for evaluation than a general request for a compact lineup.

Specify controls, metering, and operating interfaces
Describe what operators need to see and control, and which functions must be automatic, remote, or interlocked. Identify metering points, protective relays, control power, communications protocols, alarm contacts, and interfaces to building or plant systems where applicable. Provide the relevant control diagrams, point lists, and protocol requirements, while distinguishing mandatory functions from preferences that can be reviewed during design.
Document how the new assembly must coordinate with existing equipment. Useful inputs include interface drawings, device and terminal references, control-voltage expectations, network constraints, and the intended sequence of operation. Confirm who owns configuration, programming, testing, and integration tasks; do not assume those responsibilities are included in equipment manufacturing. Where a control feature depends on a particular component or software, confirm availability and compatibility for the order before treating it as a fixed design requirement.
Make interfaces and boundaries explicit
Custom equipment often depends on details beyond its enclosure. Identify upstream and downstream connections, bus or cable interfaces, neutral and grounding arrangements, external control wiring, and any provisions needed for future sections. State whether the assembly must align with existing gear and provide the manufacturer’s available interface information, because matching dimensions or connection locations cannot be assumed from a product family name alone.
Separate the equipment scope from adjacent project work. Clarify which party supplies transformers, protective-device settings, field wiring, conduit, foundations, communications infrastructure, and on-site installation or commissioning. The manufacturer’s role described here is to build and supply new equipment; do not infer installation services from a manufacturing quotation. This boundary-setting helps prevent gaps between the switchgear design, site construction documents, and the responsibilities of the electrical contractor or engineer.
Evaluate the design and quote on comparable assumptions
For a useful quote review, submit the current one-line diagram, load or feeder schedule, available fault-current data, equipment arrangement and dimensions, control requirements, applicable specifications, and delivery destination. Include revision status and identify unresolved engineering items. For Dallas–Fort Worth projects as well as orders shipping elsewhere, provide site access and receiving constraints if they affect packaging or delivery planning; regional service does not establish a local manufacturing facility or a particular delivery schedule.
Compare proposals against the same scope and assumptions: required electrical duty, physical arrangement, included devices, controls, documentation, exclusions, and items awaiting confirmation. Ask which components and ratings are confirmed, which remain subject to engineering review, and what information could change the design. Shorter lead time may be a project goal, not a guarantee; timing depends on confirmed scope, component availability, design approval, and production planning. U.S.-origin requirements also need review against the exact project specification and bill of materials.
Close open decisions before releasing the build
Before approval, reconcile drawings, schedules, control narratives, and specification notes so they describe the same configuration. Resolve discrepancies in device functions, connection locations, enclosure details, and interfaces, then identify who may authorize changes after design approval. A formal drawing review is a practical checkpoint: it lets the purchaser catch fit or coordination issues while confirming that unresolved items have an owner and a due point in the project process.
Use a written deviation and clarification record rather than relying on informal assumptions. Confirm the applicable standards, required documentation, ratings, component selection, and any project-specific acceptance criteria for the exact order. If a requirement cannot yet be verified, keep it open and establish the evidence needed to close it. This disciplined boundary between stated requirements and confirmed design decisions makes custom manufacturing more predictable without implying a particular certification, price, or completion date.
Specifications & planning
Review the details that matter for your application. Final specifications and availability should be confirmed for your project.
| Evaluation factor | Information to provide or confirm |
|---|---|
| Electrical duty | Nominal system conditions, fault-current basis, protective-device requirements; equipment ratings subject to engineering review |
| Physical fit | Room dimensions, access route, clearances, conductor entry and support constraints |
| Controls and interfaces | Required functions, communications, control power, connection points and responsibility boundaries |
| Quote basis | Drawing revisions, scope, exclusions, component availability and project-specific standards |