Power distribution, with purpose.
A useful custom switchgear specification connects the electrical design to the actual installation and operating plan. Before requesting a quote, assemble the drawings, ratings, site conditions, control interfaces and acceptance requirements that define the equipment. The checklist below helps buyers identify gaps early; final ratings, component availability, standards and scope must be confirmed for the specific order.
Start with the one-line and define the boundary
Send the latest electrical one-line diagram, marked with revision date and project status. Show the source, transformers, buses, ties, feeders, loads, grounding arrangement and any alternate operating configurations. Identify which devices and sections are included in the requested assembly, which are supplied by others, and where conductors enter and leave. A diagram that omits a future tie or temporary source can lead to an arrangement that does not match the intended operating plan.
Add an equipment location plan or elevation when available, and identify the incoming and outgoing cable or busway interfaces. State whether the request covers switchgear only or also includes accessories, metering, protection, control wiring, drawings, testing, packaging or field services. Do not assume an interface is included because it appears on a project drawing. Mark unresolved items rather than silently filling them in; the manufacturer can then identify which assumptions affect configuration, schedule or price.
Specify voltage, current and fault duty precisely
State the system nominal voltage and frequency, then request equipment ratings appropriate to that system. Nominal system voltage and an assembly’s maximum voltage rating are related but not interchangeable. Identify continuous bus and feeder current requirements, anticipated loading, and any future capacity allowance. Clarify whether load figures are measured, calculated or estimated, and whether demand, diversity or growth assumptions have already been applied.
Provide the available short-circuit current at the equipment location, the source data and the required interrupting or withstand duty for the applicable devices and assembly. Include relevant transformer impedance, utility contribution, generator operation and parallel-source cases when known. A fault value without its calculation basis can conceal a more severe operating configuration. The purchaser’s engineer and manufacturer should confirm how the specified duty maps to the proposed equipment and applicable standards; do not treat a desired rating as confirmed until the specific design is reviewed.

Describe the environment and physical constraints
Document indoor or outdoor installation, ambient temperature range, altitude, humidity, dust, corrosive exposure, water risk and ventilation conditions. Identify seismic, vibration or other site criteria where the project requires them. These conditions can influence enclosure, spacing, thermal performance and component selection, so a general description such as “industrial environment” is not a substitute for the actual exposure or project criteria.
Provide room dimensions, access routes, floor and anchoring information, working clearances required by the project design, and any limits on section size, shipping splits or final assembly. Confirm the direction and side of cable entry, phase arrangement, conduit or busway transition, and whether the equipment must align with existing gear. For a Dallas–Fort Worth site or a shipment elsewhere, the same discipline applies: share the destination constraints and delivery access information without assuming local installation or site services are part of the equipment order.
Set protection, controls and communications interfaces
For each protective device, identify the function, trip or relay requirements, current-transformer details, sensing inputs and any coordination study or protection philosophy that governs settings. Share required metering quantities, accuracy expectations, displays, alarms and control power. If settings are not yet final, identify who will provide and approve them and when they are needed. A request for a particular relay or breaker model should be checked against the actual duty, interfaces and current component availability.
Describe external control and communication connections, including protocols, network ownership, point lists, hardwired signals, interlocks and remote/local operating expectations. State which party supplies network switches, cables, software configuration and programming, and whether those items are in the requested scope. Provide interface drawings or owner standards when available. Vague phrases such as “SCADA ready” leave important work undefined; a point list and responsibility boundary make the intended handoff testable.
Make acceptance evidence and exclusions explicit
State the documents required for review and record, such as approved drawings, bills of material, wiring diagrams, nameplate data, manuals and test documentation. Define any required design review, inspection, witness testing or factory acceptance criteria, including who attends, what is demonstrated and how findings are resolved. Acceptance expectations should match the project specification and the equipment actually proposed; do not presume that a particular test, certification or listing applies without confirmation for the specific assembly.
Write down exclusions and dependencies alongside the requested deliverables. Clarify responsibility for foundations, installation, interconnecting field wiring, utility coordination, protection studies, site testing, commissioning and training. Custom builds may use American components and aim for a shorter lead time, but component availability, origin requirements, schedule and standards compliance must be verified for each order. UL 891 applies to low-voltage switchboards; it should not be presented as a general listing for medium-voltage equipment.
Work a hypothetical case into a clean RFQ handoff
Consider a hypothetical facility replacing a low-voltage distribution lineup while adding a future tie. The draft one-line shows the existing source and feeders but not whether the tie may operate closed with both sources available. That uncertainty affects fault duty and operating assumptions. Before requesting a firm design, the purchaser’s engineer should document the permitted configurations, provide the fault study basis, and identify whether the future tie is installed now or reserved as a later connection. This is a decision example, not a customer project or a claim about a completed build.
For an actionable handoff, send the revised one-line, rating schedule, site and interface drawings, control requirements, applicable project specifications, acceptance criteria and a marked list of open questions. Ask the manufacturer to identify assumptions, exclusions, proposed deviations and evidence needed to close unresolved points. Include the ship-to location and target dates for drawing review and equipment need, while recognizing that schedule is subject to confirmation. Buyers in Dallas–Fort Worth and elsewhere can use the same package to request new custom equipment; all ratings, components, standards and US-origin requirements remain order-specific.
Specifications & planning
Review the details that matter for your application. Final specifications and availability should be confirmed for your project.
| Evaluation factor | What to provide for review |
|---|---|
| Electrical basis | One-line, nominal system voltage, frequency and operating configurations |
| Duty basis | Continuous current needs, fault study source data and protection requirements |
| Site fit | Environmental conditions, dimensions, access and cable or busway interfaces |
| Acceptance and scope | Required submittals, tests, exclusions, responsible parties and open decisions |