A useful switchgear performance specification does more than name a voltage and request a price. It defines the electrical conditions, operating duties, interfaces and evidence needed to judge whether a proposed assembly fits the project. Use this checklist to make design decisions explicit before requesting a quote for new equipment.
Establish the design basis before selecting ratings
Begin with the one-line diagram and the system conditions at the equipment terminals. State the nominal system voltage, frequency, phase and wire configuration, grounding method, source arrangement and operating modes. Identify whether utility, generator, transformer or alternate sources can feed the assembly, and describe any closed-transition or parallel operation that affects available fault current. These details shape equipment selection and protective-device coordination; a voltage label alone is not a complete design basis.
Specify the available fault current, required interrupting or withstand duty, and the method and assumptions used to determine them. Include expected load, future capacity, continuous duty, ambient conditions and altitude where relevant. Keep nominal system voltage distinct from equipment maximum rating, and request confirmation that the proposed rating suits the system. A stated 5 kV, 15 kV, 27 kV or 35 kV system, for example, does not by itself establish the equipment class or acceptable rating. Ratings and standards depend on the application and must be confirmed for the specific order.
Define protection by function and coordination intent
Identify the protective functions each feeder, main and tie requires, then state the project’s coordination objectives. Depending on the design, this may involve circuit breakers or fuses, trip units or protective relays, ground-fault functions, metering and control power. Provide available settings, CT and VT requirements, trip or close control interfaces, and any communication protocol or hardwired signals needed by the broader system. Avoid naming a device without defining its duty and relationship to upstream and downstream protection.
Specify who supplies settings, performs the coordination and arc-flash studies, reviews them, and provides final approved values. The switchgear quote can define the proposed device arrangement and applicable component data, but it should not silently assume responsibility for system studies or field commissioning. Ask for the information needed to evaluate protection, such as device make and model, applicable ratings, control schematics and setting capabilities. Final selections depend on the approved study, actual system data and component availability.

Make enclosure, access and interfaces measurable
Describe indoor or outdoor use, enclosure conditions, installation environment and any project-required construction features. State the requested enclosure type or environmental protection criteria, access and maintenance clearances, cable entry direction, conduit or bus connections, room constraints and shipping or handling limits. Include seismic, corrosion, dust, moisture or temperature requirements only where the project basis calls for them. A broadly worded request such as “outdoor rated” leaves important design questions unresolved; identify the governing project requirement and ask the supplier to confirm the proposed construction against it.
Map the switchgear boundary to connected equipment. Show incoming and outgoing conductors, bus connections, grounding, neutral treatment, transformer or generator interfaces, control wiring and building-system signals. Identify what is furnished by the switchgear manufacturer and what belongs to the electrical contractor, engineer, utility or other equipment supplier. For a Dallas–Fort Worth project or a shipment elsewhere, room dimensions, access route, unloading arrangements and delivery sequence still need project-specific review; service to a region does not establish that a particular site condition has been accommodated.
Specify testing and approval evidence in advance
Name the applicable codes, standards and project specifications, and establish which documents require review before fabrication. For low-voltage switchboards, UL 891 may apply when appropriate to the assembly and project requirements; it is not a general listing for medium- or high-voltage switchgear. Do not assume a standard, certification, short-circuit rating or US-origin requirement is satisfied merely because it appears in a request. Ask the manufacturer to identify the standards and construction basis applicable to the quoted design and confirm any required evidence for the particular order.
Define factory inspection and test expectations, witness or hold points, acceptance criteria and required reports. Specify whether the submittal must include outline and floor-plan drawings, elevations, one-lines, schematics, bills of material, equipment ratings, wiring diagrams, manuals and test documentation. Clarify who reviews submittals and how comments are resolved before release to production. If a requirement cannot be verified from the proposal or documents, treat it as an open item rather than assuming compliance; approval should follow documented engineering review.
Use a worked hypothetical decision and close the gaps
Consider a hypothetical facility with a utility source, standby generator and a main-tie-main arrangement. The purchaser initially requests a particular voltage and a “high fault rating,” but has not supplied the utility fault-current letter or generator contribution. Before comparing quotes, the team obtains the one-line, confirms intended source-transfer and tie operating modes, and has the engineer establish the available fault duty. That review may change the required equipment rating, protective-device choices and interlocking scheme; the example is not a recommendation for any real installation.
For a quote, provide the current one-line, load and fault data, operating sequence, protection and metering requirements, enclosure and room constraints, connection details, applicable standards, requested documentation, approval milestones and delivery constraints. Ask the manufacturer to identify assumptions, exclusions, unresolved interfaces and evidence supporting the proposed ratings. Custom builds using American components and a shorter lead time as a goal may be relevant to the discussion, but availability, US-origin needs, standards, component selection and schedule must be validated for the specific order.
Specifications & planning
Review the details that matter for your application. Final specifications and availability should be confirmed for your project.
| Evaluation factor | What to define or verify |
|---|---|
| System basis | Nominal voltage, frequency, source modes and documented fault-current assumptions |
| Protection | Required functions, coordination responsibility, device data and control interfaces |
| Physical fit | Environment, access, connections, clearances and shipping constraints |
| Acceptance evidence | Applicable standards, submittals, test requirements and approval gates |