A sound source-transfer design starts with a one-line that shows not just where power comes from, but what the equipment should do when a source is lost, restored, or declared unsuitable. Use this checklist to make transfer assumptions visible before requesting a new switchgear build.
Map sources and define availability
Begin the conceptual one-line by identifying each normal and alternate source, its point of connection, nominal system voltage, grounding arrangement, and expected operating role. Show transformers, generators, utility service entrances, ties, and major load sections where they affect transfer. A source is not simply “available” because voltage is present: the design may also require acceptable frequency, phase sequence, voltage limits, breaker status, or a permissive from another system. State which conditions count as available and who provides each signal.
Clarify whether the arrangement is open transition, closed transition, or a project-specific sequence. Open transition disconnects one source before connecting another, so loads experience an interruption; the duration and effect depend on the switching sequence and connected equipment. Closed transition briefly parallels sources and therefore requires explicit utility acceptance, synchronism checks, protection coordination, and controls designed for that operating mode. Do not assume that a tie breaker or automatic transfer function is appropriate without reviewing the source characteristics and governing requirements.
Write the transfer sequence before selecting components
For each initiating event, describe the intended response in plain language on the design narrative and cross-reference it to the one-line. Distinguish loss of source from an alarm, planned maintenance transfer, undervoltage condition, or protective trip. Specify whether transfer is automatic or operator-initiated, what delays or permissives apply, and whether the system should retransfer when the preferred source returns. Include behavior when a source fails during transfer, a control-power supply is lost, or a breaker does not reach its commanded position.
A representative scenario might show a facility served by two utility sources with a normally open tie and separately protected load sections. If one source becomes unacceptable, approved logic could open its main breaker, verify the open condition, and then close the tie only after the alternate source and interlocks are confirmed. This is an illustrative scenario, not a recommended sequence for every installation. The engineer must determine whether the sources may be paralleled, which loads may transfer, and how recovery and manual operation should work.

Make interlocking and interruption limits explicit
Interlocking prevents an unsafe or prohibited switching state; it is not a substitute for a complete transfer philosophy. Show electrical and mechanical interlocks where required, identify the breakers involved, and state whether simultaneous closure of mains or a tie is prohibited. Confirm how control logic receives breaker position and source-quality information, how permissives are tested, and what indication is needed at the operator interface. If maintenance bypasses or local controls are contemplated, define their limits and how they preserve the intended restrictions.
Document which loads can tolerate an interruption, how long they can be without power, and whether they require a separate uninterruptible supply or staged restoration. Motor restart, inrush, process sequencing, and control-system ride-through can constrain transfer timing and alternate-source capacity. A transfer that protects service continuity may still cause nuisance trips or excessive demand if loads return together. The design basis should identify load priorities, any intentional shedding, and the party responsible for validating those assumptions.
Coordinate ratings, protection, and interfaces
For each switchboard or switchgear section, establish the system nominal voltage and the equipment’s required maximum voltage rating separately. Determine continuous current, available fault current, short-circuit withstand or interrupting requirements, bus configuration, and the ratings of mains, ties, and feeder devices from the project study and applicable equipment standards. Confirm that the proposed transfer arrangement does not create a fault-current condition beyond the selected equipment’s capability. Component availability and all ratings must be checked for the specific order.
Identify interfaces with protective relays, utility metering, generator controls, building automation, remote annunciation, and external control-power sources. Provide signal ownership, normal and fail states, required isolation, and the party furnishing wiring or communications at each boundary. Protection settings and coordination are engineering decisions; a manufacturer’s quote cannot replace the project short-circuit, coordination, or arc-flash studies. UL 891 applies to low-voltage switchboards where applicable, not to medium-voltage equipment generally, and no particular assembly compliance should be presumed without confirmation.
Prepare a quote package and approval record
A useful request for quotation includes the current one-line, source data, load schedule, transfer narrative, control schematics or sequence requirements, equipment environment, and relevant specifications. Include nominal voltage and grounding, bus and device requirements, fault-current study results, enclosure and access constraints, cable-entry preferences, metering, communications, and required documentation. Identify the project location and delivery needs; Dallas–Fort Worth projects and nationwide shipments alike require project-specific logistics and scope confirmation.
Expected review deliverables can include a marked-up one-line, proposed equipment arrangement, transfer-logic narrative, interface and responsibility schedule, device and rating schedule, and a list of exceptions or open assumptions. Ask the purchaser’s engineer and authority having jurisdiction to approve the final sequence, ratings, standards, and utility interfaces before release. The manufacturer builds and supplies new equipment, including custom configurations using American components where specified; a shorter lead time may be a goal, not a guarantee. Confirm capabilities, component availability, U.S.-origin requirements, and all project details for the order.
Specifications & planning
Review the details that matter for your application. Final specifications and availability should be confirmed for your project.
| Evaluation factor | Design question to resolve |
|---|---|
| Source availability | Which measured conditions and permissives define a usable source? |
| Transfer mode | Is interruption acceptable, and is any source paralleling authorized? |
| Interlocking | Which breaker combinations are permitted or prohibited? |
| Ratings and protection | What study data establishes required device and bus capabilities? |
| Approvals and interfaces | Who approves the sequence, utility conditions, and external signals? |